I-95 Add-A-Lane Construction in Massachusetts Continues

Construction on the Massachusetts I-95 Needham-Wellesley Add-A-Lane project began in January 2015 and is expected to be completed in Spring 2019.

Throughout the week of May 9th, 2016, MassDOT’s contractor will continue construction operations. Work will be performed project-wide during the standard working hours of 7:00 AM to 3:00 PM.

On the I-95 mainline, night work will consist of installation of drainage crossings.

The Contractor will be closing lanes during off-peak hours to continue construction of all bridges. Lane closures are permitted and are necessary to create a safe work zone; drivers are asked to be aware of possible lane closures for their own safety and that of the project team. Please also note that all work is contingent upon the weather.


For more I-95 information, visit www.i95exitguide.com, the Internet’s largest and most complete website devoted to America’s Interstate Main Street. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit from Maine to Florida!